Childcare

Sewage Pump and Drainage System Failure and Replacement

Area: Property in Mill Park

Industry
Childcare
Location
Mill Park
Outcome
2,000L removed, 2 pumps replaced
The brief

EVAC received reports for multiple plumbing issues affecting the operation of the kitchen, including:

  • Blocked kitchen drain causing sink backup
  • Floor drain overflow
  • Unable to use kitchen causing business disruption
How we delivered

Deliverables:

  • Diagnose and resolve kitchen sink backup, floor drain, and multiple fixtures across the facility
  • Investigate cause of pump station failure and grease trap overflow
  • Perform emergency liquid waste removal (2000L) from the grease trap and pump well
  • Coordinate attendance of plumber, pump technician, and electrician
  • Identify and correct electrical miswiring in pump floats
  • Replace 2x failed single-phase sewage pumps
  • Complete recommissioning and testing of pump system after installation
The outcome

Deliverables:

  • Diagnose and resolve kitchen sink backup, floor drain, and multiple fixtures across the facility
  • Investigate cause of pump station failure and grease trap overflow
  • Perform emergency liquid waste removal (2000L) from the grease trap and pump well
  • Coordinate attendance of plumber, pump technician, and electrician
  • Identify and correct electrical miswiring in pump floats
  • Replace 2x failed single-phase sewage pumps
  • Complete recommissioning and testing of pump system after installation
Childcare

Kitchen Drainage Overflow and Grease Trap Maintenance

SA
Read case study →
Childcare

Sewage Pump and Drainage System Failure and Replacement

VIC
Read case study →
Childcare

Emergency Gas Line Repair and Compliance Works

VIC
Read case study →